to a painter can finish painting a house in 8 hours. Her assistant takes 10 hours to finish the same job. How long would it take for them to complete the job if they were working together? a. 9/40 hours b. 7 hours c. 9 hours d. 4 4/9 hours

At vero eos et accusamus et iusto odio dignissimos ducimus qui blanditiis praesentium voluptatum deleniti atque corrupti quos dolores et quas molestias excepturi sint occaecati cupiditate non provident, similique sunt in culpa qui officia deserunt mollitia animi, id est laborum et dolorum fuga. Et harum quidem rerum facilis est et expedita distinctio. Nam libero tempore, cum soluta nobis est eligendi optio cumque nihil impedit quo minus id quod maxime placeat facere possimus, omnis voluptas assumenda est, omnis dolor repellendus. Itaque earum rerum hic tenetur a sapiente delectus, ut aut reiciendis voluptatibus maiores alias consequatur aut perferendis doloribus asperiores repellat.

Get our expert's

answer on brainly

SEE EXPERT ANSWER

Get your free account and access expert answers to this and thousands of other questions.

A community for students.

to a painter can finish painting a house in 8 hours. Her assistant takes 10 hours to finish the same job. How long would it take for them to complete the job if they were working together? a. 9/40 hours b. 7 hours c. 9 hours d. 4 4/9 hours

Mathematics
I got my questions answered at brainly.com in under 10 minutes. Go to brainly.com now for free help!
At vero eos et accusamus et iusto odio dignissimos ducimus qui blanditiis praesentium voluptatum deleniti atque corrupti quos dolores et quas molestias excepturi sint occaecati cupiditate non provident, similique sunt in culpa qui officia deserunt mollitia animi, id est laborum et dolorum fuga. Et harum quidem rerum facilis est et expedita distinctio. Nam libero tempore, cum soluta nobis est eligendi optio cumque nihil impedit quo minus id quod maxime placeat facere possimus, omnis voluptas assumenda est, omnis dolor repellendus. Itaque earum rerum hic tenetur a sapiente delectus, ut aut reiciendis voluptatibus maiores alias consequatur aut perferendis doloribus asperiores repellat.

Get this expert

answer on brainly

SEE EXPERT ANSWER

Get your free account and access expert answers to this and thousands of other questions

the painter paints at the rate 1 house per 8 hours; the assistant paints at the rate 1 house per 10 hours. The combined rate is 1/8+1/10 = 10/80+8/80 = 18/80 = 9/40 houses per hour.
9/40 of the house is done in one hour; how many hours to finish the house?
4 hours is 36/40; just got 4/40 left = 1/10 of an hour

Not the answer you are looking for?

Search for more explanations.

Ask your own question

Other answers:

\[rate={amount \over time} '\rightarrow' 'time={amount \over rate} = {{1'house}\over \left(9'houses \over 40'hours \right)} = {40 \over 9} hours\] \[{40 \over 9} = {9 \cdot 4 + 4 \over 9} = 4{4 \over 9}\] You can find bounds easily - it's less than half the time of the slower one, and more than half the time of the faster one, so between 4 and 5 hours.